Status
of implementation of works taken up under NFFWP recorded in the review
meeting held on 05.11.2005 at Ambassa circuit house at |
|||||
|
Depdtt
or Organisation/ IA/Sector/Project Sl. Code |
Block
Area |
Physical
Target (KM/Hect/Nos) |
Total
Project Cost (Rs. in lakhs) |
Present
status of the works & Decision taken
|
|
|
1 |
3 |
4 |
5 |
5 |
|
|
A-01-66-01 |
Dist-HQ/ ABS |
1 |
10.40 |
·
Civil work except GCI sheet roofing is complete. ·
Expenditure incurred Rs. 8.19 lakhs ·
Target for completion in all respect by Dec/2005
|
|
|
A-01-66-02 |
ABS |
1 |
4.50 |
|
|
|
A-01-66-03 |
CMN |
1 |
4.50 |
|
|
|
A-01-66-04 |
DBN |
1 |
4.50 |
|
|
|
A-01-66-05 |
MNU |
1 |
4.50 |
|
|
|
A-01-66-06 |
SLM |
1 |
9.42 |
|
|
|
A-01-66-07 |
D-HQ/ABS |
1 |
1.73 |
|
|
|
B-01-66-08 |
ABS |
25 |
16.25 |
|
|
|
B-01-66-09 |
ABS |
13
Nos. |
7.93 |
|
|
|
B-01-00-10 |
ABS |
1 |
2.65 |
|
|
|
A-01-99-11 |
MNU |
1 |
10.00 |
|
|
|
A-01-99-12 |
MNU |
1 |
9.68 |
|
|
|
Sub-Total:-EE/RD: |
|
|
86.06 |
|
|
|
C-01-00-01 |
SLM/ MNU /ABS /DBN |
7.50 Km |
32.45500 |
·
Rs. 22.50 lakhs utilized ·
Physical target against the amount placed in 1st
phase is fully achieved Projects
of 2nd phase ·
Formation & brick soling of road from Lalchari to
Dumjakrai para to be completed by Dec/2005 ·
Formation & brick soling of road from Jagabandu Para
to Bhagirat para to be completed by Dec/2005 ·
Formation & brick soling of road from Manu to AA road
to ·
Formation &
brick soling of road from Manu AA road point (near Kali Mandhir) via
Jarualcharra to be completed
by Dec/2005 |
|
|
C-01-00-02 |
MNU |
|
0.679 |
|
|
|
Sub-Total:-EE/PWD/ADC/DLI: |
|
|
33.13 |
|
|
|
D-01-11-01 |
ABS/CMN/MNU/ SLM |
0 |
6.85744 |
|
|
|
D-01-11-02 |
ABS/CMN/MNU/ SLM |
78 hect |
7.4100 |
|
|
|
Sub-Total:-DY.
MANAGER/TRPC: |
|
|
14.27 |
|
|
|
C-02-22-01 |
SLM/CMN/MNU/ABS |
|
43.0122 |
|
|
|
C-02-99-02 |
Each block |
20Nos. |
10.0000 |
·
Rs. 7.00 lakhs has been utilized so far. ·
To submit completion report indicating names of schools
November/2005. |
|
|
C-02-99-03 |
ABS/CMN/MNU/SLM |
12 Nos. |
1.1550 |
·
Rs. 1.1550 lakhs fully
utilised ·
All works completed |
|
|
C-02-66-04 |
CMN/MNU |
4 Nos. |
15.0000 |
·
Works in progress. ·
To complete all the construction works by January/2006
positively. |
|
|
C-02-22-05 |
DBN/ABS |
103 hect |
11.64800 |
· Completed · U/C be submitted immediately |
|
|
C-02-11-06 |
DBN/ABS |
25 Hect |
3.98900 |
· Completed ·
U/C be submitted immediately |
|
|
C-02-66-07 |
GNC/ABS |
4 Nos |
15.50000 |
· Rs. 8.00 lakhs so far utilized · Const. at Raishyabari, J.B.Para & Ramnagar upto roof level. · Const. at Ganganagar temporally stopped for taking up double stories barrack. |
|
|
C-02-99-08 |
DBN |
5 Nos. |
3.87600 |
· Rs. 2.78 lakhs so far utilized · Works in progress |
|
|
C-02-66-09 |
|
|
9.60483 |
·
Rs. 1.53 lakhs utilized ·
Works in progress |
|
|
Sub-Total:-
ZDO/ADC, DHALAI: |
|
|
113.79 |
|
|
|
F-01-22-01 |
CMN/MNU |
28 Nos. |
4.29109 |
·
Rs. 3.14 lakhs so far utilised |
|
|
F-01-00-02 |
CMN/MNU |
6.30 KM |
5.05000 |
·
Completed ·
To submit U/C immediately |
|
|
F-01-11-03 |
CMN/MNU |
732.65 hect |
8.26581 |
·
Work started |
|
|
F.10-55-04 |
MNU |
3 Nos. |
3.97200 |
·
Work started |
|
|
Sub-Total:-DFO/MNU: |
|
|
21.58 |
|
|
|
F-02-00-01 |
ABS |
0.323km |
1.03303 |
·
Amount fully utilized ·
To submit U/C immediately |
|
|
F-02-11-02 |
ABS/SLM |
100 HECT/ 2000 BEDS |
1.03559 |
·
Amount fully utilized ·
To submit U/C immediately |
|
|
F-02-11-03 |
ABS |
|
6.88000 |
·
To submit proposal for utilization of balance fund
covering minimum 3 kani water area per individual project by 20th
November/2005 |
|
|
F-02-22-04 |
ABS |
|
8.30000 |
·
To start work at Ruhida para immediately |
|
|
F-02-22-05 |
ABS/SLM/ DBN |
5.38 HECT |
5.89134 |
||
|
Sub-Total:-DFO/ABS: |
|
|
23.14 |
|
|
|
G-01-22-01 |
DBN |
|
3.00000 |
·
Completed ·
To submit U/C immediately |
|
|
G-01-22-02 |
DBN |
9.67 hect |
1.28494 |
·
Completed ·
To submit U/C immediately |
|
|
G-01-22-03 |
DBN |
32 hect |
8.00000 |
·
Completed ·
To submit U/C immediately |
|
|
G-02-22-04 |
SLM |
5.84 hect |
2.34811 |
·
Amount fully utilized ·
8 Nos. water bodies created & minimum size is 3 Kani ·
To submit U/C immediately |
|
|
G-02-22-05 |
ABS |
3.36 hect |
1.68014 |
·
Amount fully utilized ·
5Nos. water bodies created & minimum size is 3 Kani ·
To submit U/C immediately |
|
|
G-02-22-06 |
SLM |
1 no. |
3.00000 |
·
Work to start shortly |
|
|
G-03-22-07 |
MNU |
3.4 hect. |
2.72000 |
·
Works in progress ·
To be completed by September/05 |
|
|
G-03-22-08 |
CMN |
3.4 hect. |
2.72000 |
·
Amount fully utilized ·
Works complete ·
To submit U/C immediately |
|
|
G-00-22-09 |
ABS |
|
12.00000 |
·
Work to start shortly. |
|
|
G-00-66-10 |
SLM/MNU/ABS |
3 Nos |
15.00000 |
·
Due to non-available of rod & cement, work could not
start in due time. ·
To be completed in all respect by Feb/2005. |
|
|
G-00-22-11 |
DBN |
16 Nos. |
6.55000 |
·
Rs. 4.50 lakhs utilsed. ·
Rest amount of 2.05 lakhs will be utilized in a phased
manner. ·
16 Nos. SHGs benefited. |
|
|
G-00-22-12 |
SLM/MNU/ABS/DBN/CMN |
49.75 hect |
21.15000 |
·
Rs. 18.70 lakhs is utilized ·
Rest amount will be utilized in a phased manner. ·
To submit the total nos of project taken up under the
programme. |
|
|
G-00-22-13 |
DBN |
45 hect |
15.44000 |
·
Revised proposal received. |
|
|
Sub-Total:-Dy.
Director, Fish: |
|
|
94.89 |
|
|
|
H-01-00-01 |
MNU & CMN |
10 KM |
1.92600 |
·
Detailed report received. ·
U/C received |
|
|
H-01-22-02 |
MNU & CMN |
|
4.56500 |
·
Completed & U/C received |
|
|
H-01-00-03 |
ABS/DBN |
5 KM |
17.32500 |
·
Rs. 17.325 lakhs utilised ·
All roads are completed ·
To submit U/C immediately |
|
|
H-01-22-04 |
ABS/DBN |
|
3.00815 |
·
Rs. 3.00815 lakhs is utilized ·
To submit U/C immediately |
|
|
H-01-11-05 |
ABS/DBN |
|
5.03836 |
·
Rs. 5.03836 lakhs is utilized. ·
To submit U/C immediately |
|
|
H-01-11-06 |
ABS |
46 Hect |
7.79000 |
·
Rs. 7.79 lakhs is utilized. ·
Proposal for amount required during succeeding year’s as
a part of project for raising plantation
yet to be received. |
|
|
H-01-11-07 |
SLM |
13 Hect |
1.97000 |
||
|
H-01-11-08 |
DBN |
23 Hect |
3.11000 |
||
|
H-01-66-09 |
ABS |
1 no. |
2.54000 |
|
|
|
H-01-99-10 |
ABS/DBN/MNU |
120 Fam. |
30.00000 |
.
|
|
|
Sub-Total:-Dy.
Director, PGP: |
|
|
77.27 |
|
|
|
I-01-99-01 |
ABS |
5 Nos. |
6.23000 |
|
|
|
I-01-99-02 |
DBN |
1 no. |
1.08000 |
||
|
I-01-99-03 |
SLM |
2 Nos. |
1.69000 |
||
|
Sub-Total:-Dy.
Director, Sport: |
|
|
9.00 |
|
|
|
J-01-33-01 |
|
|
27.50 |
|
|
|
Sub-Total:-EE.
MI & FC: |
|
|
27.50 |
|
|
|
K-01-11-01 |
DBN |
5 hect |
0.80000 |
|
|
|
K-02-11-02 |
ABS/SLM |
30 hect |
4.70000 |
|
|
|
K-02-11-03 |
SLM |
20 hect |
3.23225 |
|
|
|
K-03-11-04 |
CMN |
15 hect |
2.37000 |
|
|
|
K-00-11-05 |
ABS/SLM |
60 Hect |
9.10000 |
|
|
|
K-00-11-06 |
ABS/SLM/CMN/MNU/DBN |
|
16.28200 |
·
Rs. 14.38 lakhs is utilized |
|
|
K-00-11-07 |
SLM |
15 hect |
3.23150 |
·
Work would start shortly |
|
|
Sub-Total:-Dy.
Director, Agri: |
|
|
39.72 |
|
|
|
L-00-11-01 |
MNU/CMN |
|
61.33275 |
·
Rs. 13.70 lakhs is so far utilized. |
|
|
L-02-11-02 |
ABS |
8 Hect/20 hect |
4.25740 |
·
Complete. ·
To submit U/C immediately |
|
|
L-01-11-03 |
DBN- New Kalajari |
10 hect |
8.58 |
·
Rs. 6.85 lakhs is so far utilized |
|
|
L-01-11-04 |
DBN-Ramnagar |
10 hect |
|||
|
L-01-11-05 |
DBN-Laxmipur |
10 hect |
|||
|
L-01-11-06 |
ABS/SLM /DBN |
200 hect |
48.55 |
·
In absence of finalization of rates,
fund could not utilized in due time. ·
To utilize the amount immediately as per programme. |
|
|
L-00-22-07 |
ABS |
1 |
0.20 |
·
Work in progress |
|
|
Sub-Total:-Dy.
Director, Horti: |
|
|
122.917 |
|
|
|
M-01-99-01 |
CMN/MNU/ABS |
146 Nos. |
12.04500 |
·
Rs. 1.65 lakhs is utilized so far ·
MNU-20 Nos completed ·
Target date for completion – by November/2005 |
|
|
M-01-99-02 |
DBN |
16 unit |
7.20000 |
·
Works in progress. Project would be fully implemented by
November/2005. |
|
|
M-01-99-03 |
ABS |
|
6.82200 |
·
To start the Work immediately ·
Details of component proposed under the project yet to
received. ·
Target date for completion –by Febuary/2006 |
|
|
Sub-Total:-Dy.
Director, ARDD: |
|
|
26.07 |
|
|
|
N-01-22-01 |
DBN |
|
2.00 |
·
Completed |
|
Sub-Total:-BDO/Karbook,: |
|
|
2.00 |
|
|
O-01-99-01 |
|
|
25.26 |
|
|
Sub-Total:-DFCS,: |
|
|
25.26 |
|
|
A-00-77-01 |
|
|
1.96 |
|
|
Sub-Total:-DM(D),: |
|
|
1.96 |
|
|
A-00-44-01 |
|
|
6.53 |
|
|
A-02-44-02 |
|
|
0.40 |
|
|
A-03-44-03 |
|
|
0.35 |
|
|
A-04-44-04 |
|
|
0.30 |
|
|
A-05-44-05 |
|
|
0.42 |
|
|
A-06-44-06 |
|
|
0.43 |
|
|
E-01-44-07 |
|
|
0.43 |
|
|
E-02-44-08 |
|
|
0.03 |
|
|
E-04-44-09 |
|
|
0.25 |
|
|
H-01-44-10 |
|
|
0.23 |
|
|
G-00-44-11 |
|
|
0.28 |
|
|
C-02-44-12 |
|
|
0.211 |
|
|
A-00-44-13 |
|
|
0.02 |
|
|
A-00-44-14 |
|
|
2.61 |
|
|
A-00-44-15 |
|
|
0.11 |
|