STATEMENT  SHOWING  THE  STATUS OF PROJECTS/WORKS TAKEN UP UNDER MPLADS  (LOK  SABHA) ( AS ON 30.11.2005)
(Rs. In lakhs)
Sl. No. Name of work Date of fund placed Amount (Rs. in lakhs) Name of I/O. Name of Sub-Divn. Fund place to I/O Expenditure so far incurred  Status of work Name of constitancy Remarks
1 2 3 4 5 6     7 8  
1 Construction of Comminuty Hall 300 seated at Salema. 02.02.2001 10.00 BDO,SLM. KMP 10.00 10.00 50% completed. Salema Comminicated for addl. Fund07.09.05.
Sub-Total   10.00     10.00 10.00      
2 Constn.of 300 seated Community Hall at Manikbhandar under KMP 5.2.02 19.00 BDO,SLM. KMP 19.00 19.00 40% completed. Kamalpur Comminicated for addl. Fund07.09.05.  
3 Const. Of Maracharra PHC building for addl. accommodation. 25.02.01 3.00 EE. RD. DLI KMP 3.00 2.50 Not reported by I/A Kamalpur  
4 Const. Of Madrasa High School. 04.12.01 8.00 EO. N/P. KMP KMP 8.00 8.00 Not reported by I/A Kamalpur Comminicated for addl. Fund07.09.05.
Sub-Total   30.00     30.00 29.50      
5 Construction of 300 seated Community Hall at Raishyabari 02.02.2001 10.00 BDO, DBN GNC 10.00 10.00 Not reported by BDO Raima  
Sub-Total   10.00     10.00 10.00      
6 Constn. Of 300 seated Community Hall at Manughat under LTV. 19.03.02 17.25 BDO,MNU LTV 10.00 10.00 Not reported Chawmanu Comminicated for addl. Fund07.09.05.
7 Construction of Comminuty Hall 300 seated at Chawmanu. _ 11.465 EE,KGT.. LTV 11.47 11.47 Not reported Chawmanu  
8 Construction of Chailengta Town Hall  - 31.200 EE,KGT.. LTV 31.20 31.20 Not reported Chawmanu  
9 Construction of building of Lalcherra PHC. Under LTV. 06.04.05 5.00 BDO, MNU LTV 5.00 0.00 Not reported Chawmanu  
10 Construction of Tribal Rest House at Manikpur. 06.04.05 4.00 BDO, CMN LTV 4.00 1.00 Not reported Chawmanu  
Sub-Total   68.92     61.67 53.67      
Grand Total:   118.92     111.67 103.17      
STATEMENT  SHOWING  THE  STATUS PROJECTS/WORKS TAKEN UP UNDER MPLADS  (RAJYA  SABHA) (AS ON 30.11.2005)
Sl. No. Name of work Date of fund placed Amount (Rs. in lakhs) Name of I/O. Name of Sub-Divn. Fund place to I/O Expenditure so far incurred  Progress of work Remarks 
1 2 3 4 5 6 7 8 9 10
Name of MP:- Matilal Sarkar                
1 Construction of Sridhampur H/S School 6.11.03 & 16.9.05 12.10 BDO, SLM KMP 12.10 12.10 50% completed.  
2 Const. of 20 nos. unemployed Shed at Manikbhander 08.04.04 & 16.9.05 14.70698 BDO,SLM KMP 14.70698 14.71 80% Completed.  
3 Construction of Market Stall at Masli Bazar under LTV Sub-Div. 18.10.04 4.00 BDO. MNU LTV 4.00   Not reported  
4 Construction of Cultural Hall at 82 Miles under Manu Block 3.6.2005 & 14.9.05 10.00 BDO. MNU LTV 10.00   Not reported  
5 Construction of Pucca bridge over Karamcherra at Roaja para under Manu Block. 3.6.2005 & 14.9.05 10.00 EE. PWD, TTAADC Dli. LTV 10.00   Not reported  
TOTAL :-   50.80698     50.80698 26.81